What You Need for a Building Permit in Brookline, MA
To get a building permit in Brookline, apply to the Building Department through Accela online permits. For a new home or addition you will usually need the application, scaled plans, a surveyor's plot plan, contractor license and insurance paperwork (or a homeowner exemption), a workers' comp affidavit and energy code documentation. Brookline follows the Specialized (Opt-In) Energy Code, so new homes and large additions also need a projected HERS rating report from a RESNET-certified rater at permit and a confirmed HERS rating before the certificate of occupancy.
Brookline building department
Building Department
333 Washington Street, Brookline, MA 02445
(617) 730-2100
Apply: Accela online permits
Brookline Building Permit Checklist
What Brookline asks for on a new home, addition or major renovation, from the Brookline permit pages. Bring all of it the first time and the review moves faster.
- Online building permit application in Accela
- Electronic plans sealed by an architect and/or registered land surveyor (for plan review and any ZBA filing)
- Registry-stamped ZBA decision when zoning relief was granted
- Fire protection plans go to Brookline Fire for review
- Energy code documentation; new homes must use the all-electric path under the Fossil Fuel Free bylaw

Who Can Apply and How
Building permits are filed online through Accela (an account is required).
Apply through Accela online permits. Questions go to the Building Department at (617) 730-2100.
Energy Code Compliance: The Part That Holds Up Most Permits
Brookline is on the state's Specialized Code list and has followed a Stretch Code since 2011.
At permit: New homes and large additions need a projected HERS rating report. Under Brookline's Fossil Fuel Free rule (effective February 20, 2024), new construction can't use the Specialized Code's Zero Energy or Mixed-Fuel paths, and major renovations can't add combustion equipment.
At final: Brookline's CO checklist requires energy compliance documents (acceptance documents, certifications and confirmations), which is where the confirmed HERS certificate and test results go.
| Project | Energy document |
|---|---|
| New home | Projected HERS report (HERS 42 mixed-fuel / 45 all-electric) |
| ADU | Projected HERS report (HERS 52 / 55) |
| Addition over 1,000 sq ft or over 100% of the home | Projected HERS report (HERS 65 / 70) |
| Smaller addition or alteration | REScheck or the prescriptive path, if the inspector accepts it |
| Commercial up to 20,000 sq ft | COMcheck plus a whole-building blower door test |
Home Energy Efficiency Consultants prepares the projected HERS report from your plans, usually in about one business day after the quote is accepted, then does the pre-drywall inspection, blower door and duct leakage tests and the confirmed HERS certificate. See our stretch code report for Brookline permits page for what's in the report, EV-ready and solar-ready rules, and when Phius applies.


Other Approvals You May Need in Brookline
- Planning Board and ZBA for zoning relief (denial letter within 30 days of filing)
- Preservation Commission demolition review for full demolition or removing 25%+ of the exterior; up to 12-month delay
- Preservation Commission for work in a Local Historic District
- Fire Department for fire protection systems
Permit Fees and Timing
Fees: $20 per $1,000, minimum $50. Certificate of occupancy $50 per dwelling unit (fee schedule effective July 18, 2022). Always check the current schedule before you apply.
Review time: For zoning relief cases, the denial letter comes within 30 days of filing.
Final Inspection and Certificate of Occupancy
All inspections passed, a CO request letter, final affidavits on town forms, fire protection test documents, energy compliance documents, structural engineer's final report, zoning compliance statement and a job card signed off by all departments.
For new homes and large additions, the confirmed HERS rating (with passing blower door and duct leakage results) is part of the close-out paperwork. Book the final test before the building inspector's final so the paperwork is ready.
Local rules to know:
- Fossil Fuel Free bylaw in effect since February 20, 2024
- Demolition delay applies to all buildings
Building Permit FAQ for Brookline
What do you need for a building permit in Brookline, MA?
For a new home or addition: the online application, scaled construction plans, a certified plot plan by a land surveyor, contractor CSL/HIC, insurance and workers' comp paperwork (or a homeowner exemption), any zoning or historic approvals, and energy code compliance documentation. New homes and large additions need a projected HERS rating report.
Do I need a HERS rating for a building permit in Brookline?
For a new home, yes, and also for additions over 1,000 sq ft or more than 100% of the existing home. The rater models your plans for the permit (projected HERS report), then tests the finished house (blower door and duct leakage) for the confirmed HERS rating. Smaller additions and alterations can usually use REScheck or the prescriptive path.
What energy code does Brookline follow?
Brookline is on the state's Specialized Code list and has followed a Stretch Code since 2011.
Where do I apply for a building permit in Brookline?
At the Building Department, 333 Washington Street, Brookline, MA 02445 ((617) 730-2100), through Accela online permits.
Who can pull a building permit in Brookline?
Building permits are filed online through Accela (an account is required).
How much does a building permit cost in Brookline?
$20 per $1,000, minimum $50. Certificate of occupancy $50 per dwelling unit (fee schedule effective July 18, 2022). Check the current fee schedule before you apply.
How long does a building permit take in Brookline?
For zoning relief cases, the denial letter comes within 30 days of filing.
Sources and Related Pages
Checked on Brookline's official pages in October 2026. Rules and fees change, so confirm with the building department before you file.
- Brookline online permits
- Brookline fee schedule
- Brookline Fossil Fuel Free buildings
- Mass.gov: energy code adoption by municipality
Related: Stretch code report for permitting · HERS rating in Brookline · Blower door testing · What triggers a HERS rating. We cover Brookline from our Somerville office at 519 Broadway.
Need the Energy Report for Your Brookline Permit?
Send your plans today. Most projected HERS reports are ready in about one business day after the quote is accepted.
Mass Save®-Listed HERS Rater
Trusted Partner — Verified
Partner
Passive House Verifier
Member★★★★★136 Google
Reviews
The Phius Certified Verifier logo is used under license from Phius.