What You Need for a Building Permit in Charlestown, MA
To get a building permit in Charlestown (Boston), apply to the Boston Inspectional Services Department (ISD) through Boston ISD online permit portal. For a new home or addition you will usually need the application, scaled plans, a surveyor's plot plan, contractor license and insurance paperwork (or a homeowner exemption), a workers' comp affidavit and energy code documentation. Charlestown follows the Specialized (Opt-In) Energy Code, so new homes and large additions also need a projected HERS rating report from a RESNET-certified rater at permit and a confirmed HERS rating before the certificate of occupancy.
Charlestown building department
Boston Inspectional Services Department (ISD) - Charlestown has no separate permit office
1010 Massachusetts Avenue, 5th Floor, Boston, MA 02118
617-635-5300
Apply: Boston ISD online permit portal
Charlestown Building Permit Checklist
What Charlestown asks for on a new home, addition or major renovation, from the City of Boston permit pages. Bring all of it the first time and the review moves faster.
- Online long-form application through Boston ISD with full scope and total estimated cost
- Stamped, scaled design plans (plot plan, elevations and floor plans for zoning review; structural, fire protection, MEP and energy plans for building review)
- Certified plot plan by a Massachusetts Registered Land Surveyor for new homes and additions
- Contractor license, liability insurance, workers' comp affidavit, signed contract, Site Safety Plan Affidavit and Mattocks-Higgins Affidavit
- Flood zone affidavit and elevation certificate where the lot is in a flood zone

Who Can Apply and How
Same as the rest of Boston: the licensed contractor applies in their own name, or the owner of an owner-occupied 1-2 family home can apply with the Homeowner Construction License Exemption form and workers' comp affidavit.
Apply through Boston ISD online permit portal. Questions go to the Boston Inspectional Services Department (ISD) - Charlestown has no separate permit office at 617-635-5300.
Energy Code Compliance: The Part That Holds Up Most Permits
Charlestown is part of Boston, which adopted the Specialized (Opt-In) Energy Code effective January 1, 2024.
At permit: Energy plans go in with building review. New homes and large additions need a projected HERS rating report from a RESNET-certified rater.
At final: Boston ISD reviews HERS compliance before issuing the certificate of occupancy for new homes and additions over 1,000 sq ft.
| Project | Energy document |
|---|---|
| New home | Projected HERS report (HERS 42 mixed-fuel / 45 all-electric) |
| ADU | Projected HERS report (HERS 52 / 55) |
| Addition over 1,000 sq ft or over 100% of the home | Projected HERS report (HERS 65 / 70) |
| Smaller addition or alteration | REScheck or the prescriptive path, if the inspector accepts it |
| Commercial up to 20,000 sq ft | COMcheck plus a whole-building blower door test |
Home Energy Efficiency Consultants prepares the projected HERS report from your plans, usually in about one business day after the quote is accepted, then does the pre-drywall inspection, blower door and duct leakage tests and the confirmed HERS certificate. See our stretch code report for Boston permits page for what's in the report, EV-ready and solar-ready rules, and when Phius applies.


Other Approvals You May Need in Charlestown
- Boston zoning review (Charlestown is zoned under Article 62, the Charlestown Neighborhood District); Zoning Board of Appeal if relief is needed
- Article 85 demolition delay for buildings 50+ years old
- Monument Square Landmark District: proposed as Charlestown's first local historic district and still under study in fall 2026. If it is designated, exterior changes inside it would need Landmarks Commission review
- Boston Water & Sewer Commission, Public Works (curb cuts) and Parks (within 100 ft of a park) as needed
Permit Fees and Timing
Fees: Boston rates: $50 plus $10 per $1,000 of estimated cost for a long-form permit. Always check the current schedule before you apply.
Review time: About 4 to 5 weeks for a complete long-form application with no relief needed (Boston ISD).
Final Inspection and Certificate of Occupancy
Same as Boston: final inspections with the contractor on site, trade sign-offs, final cost, HERS compliance and flood/BWSC paperwork where needed.
For new homes and large additions, the confirmed HERS rating (with passing blower door and duct leakage results) is part of the close-out paperwork. Book the final test before the building inspector's final so the paperwork is ready.
Local rules to know:
- Many Charlestown homes are older row houses and triple-deckers. Gut renovations and additions over 1,000 sq ft can trigger a HERS rating, so check early
Building Permit FAQ for Charlestown
What do you need for a building permit in Charlestown, MA?
For a new home or addition: the online application, scaled construction plans, a certified plot plan by a land surveyor, contractor CSL/HIC, insurance and workers' comp paperwork (or a homeowner exemption), any zoning or historic approvals, and energy code compliance documentation. New homes and large additions need a projected HERS rating report.
Do I need a HERS rating for a building permit in Charlestown?
For a new home, yes, and also for additions over 1,000 sq ft or more than 100% of the existing home. The rater models your plans for the permit (projected HERS report), then tests the finished house (blower door and duct leakage) for the confirmed HERS rating. Smaller additions and alterations can usually use REScheck or the prescriptive path.
What energy code does Charlestown follow?
Charlestown is part of Boston, which adopted the Specialized (Opt-In) Energy Code effective January 1, 2024.
Where do I apply for a building permit in Charlestown?
At the Boston Inspectional Services Department (ISD) - Charlestown has no separate permit office, 1010 Massachusetts Avenue, 5th Floor, Boston, MA 02118 (617-635-5300), through Boston ISD online permit portal.
Who can pull a building permit in Charlestown?
Same as the rest of Boston: the licensed contractor applies in their own name, or the owner of an owner-occupied 1-2 family home can apply with the Homeowner Construction License Exemption form and workers' comp affidavit.
How much does a building permit cost in Charlestown?
Boston rates: $50 plus $10 per $1,000 of estimated cost for a long-form permit. Check the current fee schedule before you apply.
How long does a building permit take in Charlestown?
About 4 to 5 weeks for a complete long-form application with no relief needed (Boston ISD).
Sources and Related Pages
Checked on Charlestown's official pages in October 2026. Rules and fees change, so confirm with the building department before you file.
- Boston: how to get a long form permit
- Boston Landmarks: Monument Square Landmark District FAQ
- Boston: Article 85 demolition delay
- Mass.gov: energy code adoption by municipality
Related: Stretch code report for permitting · HERS rating in Boston · Blower door testing · What triggers a HERS rating. We cover Charlestown from our Everett office at 371 Main St.
Need the Energy Report for Your Charlestown Permit?
Send your plans today. Most projected HERS reports are ready in about one business day after the quote is accepted.
Mass Save®-Listed HERS Rater
Trusted Partner — Verified
Partner
Passive House Verifier
Member★★★★★136 Google
Reviews
The Phius Certified Verifier logo is used under license from Phius.