To get a building permit in Needham, apply to the Building Department through OpenGov. For a new home or addition you will usually need the application, scaled plans, a surveyor's plot plan, contractor license and insurance paperwork (or a homeowner exemption), a workers' comp affidavit and energy code documentation. Needham follows the Specialized (Opt-In) Energy Code, so new homes and large additions also need a projected HERS rating report from a RESNET-certified rater at permit and a confirmed HERS rating before the certificate of occupancy.
Needham building department
Building Department
500 Dedham Avenue, Needham, MA 02492
781-455-7550
Apply: OpenGov (ViewPoint Cloud) - paper applications not accepted
Needham Building Permit Checklist
What Needham asks for on a new home, addition or major renovation, from the Needham permit pages. Bring all of it the first time and the review moves faster.
- Online building permit application
- Workers' Compensation Insurance Affidavit and Debris Removal Form
- Plot plan on the Town of Needham form, certified by a Massachusetts Registered Land Surveyor (5 originals); an as-built is required before framing
- Proof of ownership (deed)
- 2 sets of scaled construction drawings (stamped for engineered materials or unique design)
- Energy Conservation Form plus energy compliance (HERS rating for new homes)
- Fire Department smoke detector permit (additions) and Existing Structure Affidavit (new construction with a house still standing)

Who Can Apply and How
Contractors need a current CSL and HIC registration (copies required). A homeowner can pull the permit with the Homeowners Exemption Eligibility Affidavit.
Apply through OpenGov (ViewPoint Cloud) - paper applications not accepted. Questions go to the Building Department at 781-455-7550.
Energy Code Compliance: The Part That Holds Up Most Permits
Needham's Specialized Code took effect July 1, 2024 for new construction. Additions and renovations still follow the Stretch Code.
At permit: New homes need a projected HERS rating. Mixed-fuel 1-2 family homes need 4 kW of solar per unit (shading exception), and homes over 4,000 sq ft must be all-electric or net zero.
At final: Before the final building inspection Needham requires the final HERS rating (if applicable), a blower door test and a duct leakage test (if applicable).
| Project | Energy document |
|---|---|
| New home | Projected HERS report (HERS 42 mixed-fuel / 45 all-electric) |
| ADU | Projected HERS report (HERS 52 / 55) |
| Addition over 1,000 sq ft or over 100% of the home | Projected HERS report (HERS 65 / 70) |
| Smaller addition or alteration | REScheck or the prescriptive path, if the inspector accepts it |
| Commercial up to 20,000 sq ft | COMcheck plus a whole-building blower door test |
Home Energy Efficiency Consultants prepares the projected HERS report from your plans, usually in about one business day after the quote is accepted, then does the pre-drywall inspection, blower door and duct leakage tests and the confirmed HERS certificate. See our stretch code report for permitting page for what's in the report, EV-ready and solar-ready rules, and when Phius applies.


Other Approvals You May Need in Needham
- DPW/Engineering (utilities, easements, wetlands, floodplain) and DPW Water and Sewer
- DPW street occupancy permit for curb, excavation and driveway work (Dig Safe required)
- Conservation Commission near wetlands, floodplain or Riverfront Area
- Health Department for demolition and septic
Permit Fees and Timing
Fees: $10 per $1,000 of estimated cost, minimum $150 for 1-2 family. CO (no renovation) $100. Always check the current schedule before you apply.
Final Inspection and Certificate of Occupancy
Grades Card Circulation Form, 3 copies of the final as-built with height and survey records, final HERS rating, blower door test and duct leakage test.
For new homes and large additions, the confirmed HERS rating (with passing blower door and duct leakage results) is part of the close-out paperwork. Book the final test before the building inspector's final so the paperwork is ready.
Local rules to know:
- New construction: Specialized Code. Additions and renovations: Stretch Code
Building Permit FAQ for Needham
What do you need for a building permit in Needham, MA?
For a new home or addition: the online application, scaled construction plans, a certified plot plan by a land surveyor, contractor CSL/HIC, insurance and workers' comp paperwork (or a homeowner exemption), any zoning or historic approvals, and energy code compliance documentation. New homes and large additions need a projected HERS rating report.
Do I need a HERS rating for a building permit in Needham?
For a new home, yes, and also for additions over 1,000 sq ft or more than 100% of the existing home. The rater models your plans for the permit (projected HERS report), then tests the finished house (blower door and duct leakage) for the confirmed HERS rating. Smaller additions and alterations can usually use REScheck or the prescriptive path.
What energy code does Needham follow?
Needham's Specialized Code took effect July 1, 2024 for new construction. Additions and renovations still follow the Stretch Code.
Where do I apply for a building permit in Needham?
At the Building Department, 500 Dedham Avenue, Needham, MA 02492 (781-455-7550), through OpenGov (ViewPoint Cloud) - paper applications not accepted.
Who can pull a building permit in Needham?
Contractors need a current CSL and HIC registration (copies required). A homeowner can pull the permit with the Homeowners Exemption Eligibility Affidavit.
How much does a building permit cost in Needham?
$10 per $1,000 of estimated cost, minimum $150 for 1-2 family. CO (no renovation) $100. Check the current fee schedule before you apply.
Sources and Related Pages
Checked on Needham's official pages in October 2026. Rules and fees change, so confirm with the building department before you file.
- Needham: new construction
- Needham: home addition
- Needham: Specialized Stretch Energy Code
- Mass.gov: energy code adoption by municipality
Related: Stretch code report for permitting · HERS rating in Needham · Blower door testing · What triggers a HERS rating. We cover Needham from our Framingham office at 68 South St.
Need the Energy Report for Your Needham Permit?
Send your plans today. Most projected HERS reports are ready in about one business day after the quote is accepted.
Mass Save®-Listed HERS Rater
Trusted Partner — Verified
Partner
Passive House Verifier
Member★★★★★136 Google
Reviews
The Phius Certified Verifier logo is used under license from Phius.