What You Need for a Building Permit in Reading, MA
To get a building permit in Reading, apply to the Building Division through OpenGov online permitting. For a new home or addition you will usually need the application, scaled plans, a surveyor's plot plan, contractor license and insurance paperwork (or a homeowner exemption), a workers' comp affidavit and energy code documentation. Reading follows the base Massachusetts energy code (2021 IECC with state amendments), so new homes show energy compliance either prescriptively (REScheck) or with a HERS rating from a RESNET-certified rater.
Reading building department
Building Division
Town Hall, 16 Lowell Street, Reading, MA 01867
781-942-6613
Apply: OpenGov online permitting
Reading Building Permit Checklist
What Reading asks for on a new home, addition or major renovation, from the Reading permit pages. Bring all of it the first time and the review moves faster.
- Online application with the full estimated cost
- Certified plot plan (two for additions)
- Two sets of building plans (stamped plans may be required)
- Energy form for new homes and additions
- HERS rater for new homes
- Manual J and S for new ductwork or mini-splits (Manual J, S and D for a new home)
- Window order and kitchen hood specs (hoods over 400 CFM need make-up air)
- Contract, CSL, HIC, workers' comp and insurance, or the homeowner exemption forms

Who Can Apply and How
Contractors upload a signed contract, CSL, HIC and workers' comp certificate. Homeowners who live or intend to live at the property upload the CSL and HIC exemptions, workers' comp affidavit and a notarized Estimated Cost Affidavit, and must attend all inspections.
Apply through OpenGov online permitting. Questions go to the Building Division at 781-942-6613.
Energy Code Compliance in Reading
Reading is not on the state's Specialized or Stretch adopter lists; the town says the 2021 IECC took effect for residential on January 1, 2023.
At permit: Reading asks for an energy form for new homes and additions and a HERS rater for new homes. An insulation certificate must be approved before the insulation inspection, and the HERS rater must confirm in writing that they were present during installation.
At final: At final we run the blower door and duct leakage tests and issue the confirmed HERS certificate.
| Project | Energy document |
|---|---|
| New home | REScheck/prescriptive, or a HERS rating (Energy Rating Index path) |
| ADU | REScheck/prescriptive, or a HERS rating |
| Addition over 1,000 sq ft or over 100% of the home | REScheck/prescriptive, or a HERS rating |
| Smaller addition or alteration | REScheck or the prescriptive path, if the inspector accepts it |
| Commercial up to 20,000 sq ft | COMcheck plus a whole-building blower door test |
Home Energy Efficiency Consultants prepares the projected HERS report from your plans, usually in about one business day after the quote is accepted, then does the pre-drywall inspection, blower door and duct leakage tests and the confirmed HERS certificate. See our stretch code report for permitting page for what's in the report, EV-ready and solar-ready rules, and when Phius applies.


Other Approvals You May Need in Reading
- Conservation, Engineering and Fire for a new home (Engineering assigns the address and approves the curb cut)
- Fire Department plan approval for bedroom additions and attached garages
- Engineering in the Aquifer Protection Overlay District
- Historic District Commission in the Historic District; demolition delay for listed structures
Permit Fees and Timing
Fees: Residential: $13 per $1,000, minimum $50. Certificate of Occupancy $50 per unit (revised July 1, 2024). Always check the current schedule before you apply.
Review time: Issued or denied within 30 days of a complete submittal.
Final Inspection and Certificate of Occupancy
Before the final, upload the permit card with electrical, plumbing and fire sign-offs and a notarized Final Cost of Construction Affidavit.
For new homes and large additions, the confirmed HERS rating (with passing blower door and duct leakage results) is part of the close-out paperwork. Book the final test before the building inspector's final so the paperwork is ready.
Local rules to know:
- Town Hall is closed Fridays
Building Permit FAQ for Reading
What do you need for a building permit in Reading, MA?
For a new home or addition: the online application, scaled construction plans, a certified plot plan by a land surveyor, contractor CSL/HIC, insurance and workers' comp paperwork (or a homeowner exemption), any zoning or historic approvals, and energy code compliance documentation. New homes and large additions need a projected HERS rating report.
Do I need a HERS rating for a building permit in Reading?
Not always. Reading follows the base energy code, so a new home can comply prescriptively (REScheck) or with a HERS rating. Reading itself asks for a HERS rater on new homes. A HERS rating gives more design flexibility and is required for Mass Save new construction incentives and ENERGY STAR. New homes still need a blower door test.
What energy code does Reading follow?
Reading is not on the state's Specialized or Stretch adopter lists; the town says the 2021 IECC took effect for residential on January 1, 2023.
Where do I apply for a building permit in Reading?
At the Building Division, Town Hall, 16 Lowell Street, Reading, MA 01867 (781-942-6613), through OpenGov online permitting.
Who can pull a building permit in Reading?
Contractors upload a signed contract, CSL, HIC and workers' comp certificate. Homeowners who live or intend to live at the property upload the CSL and HIC exemptions, workers' comp affidavit and a notarized Estimated Cost Affidavit, and must attend all inspections.
How much does a building permit cost in Reading?
Residential: $13 per $1,000, minimum $50. Certificate of Occupancy $50 per unit (revised July 1, 2024). Check the current fee schedule before you apply.
How long does a building permit take in Reading?
Issued or denied within 30 days of a complete submittal.
Sources and Related Pages
Checked on Reading's official pages in October 2026. Rules and fees change, so confirm with the building department before you file.
- Reading permitting information
- Reading residential permit checklist (PDF)
- Reading building permit fees (2024)
- Mass.gov: energy code adoption by municipality
Related: Stretch code report for permitting · HERS rating in Reading · Blower door testing · What triggers a HERS rating. We cover Reading from our Everett office at 371 Main St.
Need the Energy Report for Your Reading Permit?
Send your plans today. Most projected HERS reports are ready in about one business day after the quote is accepted.
Mass Save®-Listed HERS Rater
Trusted Partner — Verified
Partner
Passive House Verifier
Member★★★★★136 Google
Reviews
The Phius Certified Verifier logo is used under license from Phius.