What You Need for a Building Permit in Stoneham, MA
To get a building permit in Stoneham, apply to the Building Department through OpenGov. For a new home or addition you will usually need the application, scaled plans, a surveyor's plot plan, contractor license and insurance paperwork (or a homeowner exemption), a workers' comp affidavit and energy code documentation. Stoneham follows the Stretch Energy Code, so new homes and large additions also need a projected HERS rating report from a RESNET-certified rater at permit and a confirmed HERS rating before the certificate of occupancy.
Stoneham building department
Building Department
35 Central Street, Garden Level, Stoneham, MA 02180
781-279-2670
Apply: OpenGov - Building Permit Residential (1 and 2 family)
Stoneham Building Permit Checklist
What Stoneham asks for on a new home, addition or major renovation, from the Stoneham permit pages. Bring all of it the first time and the review moves faster.
- Application signed off by the Treasurer, plus BOH, DPW and Conservation where they apply
- Workers' comp affidavit, license copies, contract and certificate of insurance
- Architectural plans to scale; Fire Department-stamped plans if bedrooms are added or the layout changes
- Structural plans with members, spans, engineered lumber reports and wall bracing
- Elevations with heights and roof pitches
- New homes and additions over 1,000 sf: energy compliance with envelope R-values and HERS certification, plus solar-ready and EV locations and radon system detail
- Certified plot plan stamped by a Professional Land Surveyor

Who Can Apply and How
A licensed CSL holder and/or registered HIC applies, or a homeowner who supervises the whole project and attends all inspections. The owner signs an authorization if an agent applies.
Apply through OpenGov - Building Permit Residential (1 and 2 family). Questions go to the Building Department at 781-279-2670.
Energy Code Compliance: The Part That Holds Up Most Permits
Stoneham adopted the Stretch Code in 2017 (effective July 1, 2017) and is not on the state's Specialized list.
At permit: Stoneham's Required Document Guide asks new homes and additions over 1,000 sf for energy code compliance with envelope R-values and HERS certification, plus solar-ready and EV locations.
At final: At final we run the blower door and duct leakage tests and issue the confirmed HERS certificate.
| Project | Energy document |
|---|---|
| New home | Projected HERS report (HERS 42 mixed-fuel / 45 all-electric) |
| ADU | Projected HERS report (HERS 52 / 55) |
| Addition over 1,000 sq ft or over 100% of the home | Projected HERS report (HERS 65 / 70) |
| Smaller addition or alteration | REScheck or the prescriptive path, if the inspector accepts it |
| Commercial up to 20,000 sq ft | COMcheck plus a whole-building blower door test |
Home Energy Efficiency Consultants prepares the projected HERS report from your plans, usually in about one business day after the quote is accepted, then does the pre-drywall inspection, blower door and duct leakage tests and the confirmed HERS certificate. See our stretch code report for permitting page for what's in the report, EV-ready and solar-ready rules, and when Phius applies.


Other Approvals You May Need in Stoneham
- Treasurer approval on every application
- Board of Health, DPW and Conservation Commission where applicable
- Fire Department plan stamp for new bedrooms or layout changes
- Demolition affidavit for demolition
Permit Fees and Timing
Fees: 1-2 family: $13 per $1,000, minimum $55; plan review for new 1-2 family $100; CO $50 (effective January 1, 2026). Always check the current schedule before you apply.
Review time: Up to 30 days; new buildings take close to the full 30.
Final Inspection and Certificate of Occupancy
Inspections at each stage on the card. For new houses, a certified as-built plot plan is due after the foundation, before framing.
For new homes and large additions, the confirmed HERS rating (with passing blower door and duct leakage results) is part of the close-out paperwork. Book the final test before the building inspector's final so the paperwork is ready.
Local rules to know:
- A permit lapses if work doesn't begin within 180 days
Building Permit FAQ for Stoneham
What do you need for a building permit in Stoneham, MA?
For a new home or addition: the online application, scaled construction plans, a certified plot plan by a land surveyor, contractor CSL/HIC, insurance and workers' comp paperwork (or a homeowner exemption), any zoning or historic approvals, and energy code compliance documentation. New homes and large additions need a projected HERS rating report.
Do I need a HERS rating for a building permit in Stoneham?
For a new home, yes, and also for additions over 1,000 sq ft or more than 100% of the existing home. The rater models your plans for the permit (projected HERS report), then tests the finished house (blower door and duct leakage) for the confirmed HERS rating. Smaller additions and alterations can usually use REScheck or the prescriptive path.
What energy code does Stoneham follow?
Stoneham adopted the Stretch Code in 2017 (effective July 1, 2017) and is not on the state's Specialized list.
Where do I apply for a building permit in Stoneham?
At the Building Department, 35 Central Street, Garden Level, Stoneham, MA 02180 (781-279-2670), through OpenGov - Building Permit Residential (1 and 2 family).
Who can pull a building permit in Stoneham?
A licensed CSL holder and/or registered HIC applies, or a homeowner who supervises the whole project and attends all inspections. The owner signs an authorization if an agent applies.
How much does a building permit cost in Stoneham?
1-2 family: $13 per $1,000, minimum $55; plan review for new 1-2 family $100; CO $50 (effective January 1, 2026). Check the current fee schedule before you apply.
How long does a building permit take in Stoneham?
Up to 30 days; new buildings take close to the full 30.
Sources and Related Pages
Checked on Stoneham's official pages in October 2026. Rules and fees change, so confirm with the building department before you file.
- Stoneham required document guide
- Stoneham fee schedule (2026)
- Stoneham Building Department FAQs
- Mass.gov: energy code adoption by municipality
Related: Stretch code report for permitting · HERS rating in Stoneham · Blower door testing · What triggers a HERS rating. We cover Stoneham from our Everett office at 371 Main St.
Need the Energy Report for Your Stoneham Permit?
Send your plans today. Most projected HERS reports are ready in about one business day after the quote is accepted.
Mass Save®-Listed HERS Rater
Trusted Partner — Verified
Partner
Passive House Verifier
Member★★★★★136 Google
Reviews
The Phius Certified Verifier logo is used under license from Phius.