What You Need for a Building Permit in Wellesley, MA
To get a building permit in Wellesley, apply to the Building Department through ViewPoint Cloud. For a new home or addition you will usually need the application, scaled plans, a surveyor's plot plan, contractor license and insurance paperwork (or a homeowner exemption), a workers' comp affidavit and energy code documentation. Wellesley follows the Specialized (Opt-In) Energy Code, so new homes and large additions also need a projected HERS rating report from a RESNET-certified rater at permit and a confirmed HERS rating before the certificate of occupancy.
Wellesley building department
Building Department
888 Worcester Street, Suite 160, Wellesley, MA 02482
781-431-1019
Apply: ViewPoint Cloud (OpenGov)
Wellesley Building Permit Checklist
What Wellesley asks for on a new home, addition or major renovation, from the Wellesley permit pages. Bring all of it the first time and the review moves faster.
- Residential Building Permit Application (1-2 family) with proof of ownership, owner signature and estimated cost
- Certified plot plan signed by a Massachusetts Registered Land Surveyor for new homes, additions and footprint changes (mortgage plot plans not accepted)
- 500-foot bylaw letter for new homes and additions encroaching on the front setback
- Large House Review (TLAG) affidavit for new single-family homes and additions increasing TLAG by more than 10%
- Construction plans no larger than 24x36 (stamped for trusses, engineered lumber, steel or unique design)
- Energy code documentation
- Solid waste disposal application and workers' comp affidavit
- Two sets of Fire Department-stamped plans for new homes, bedroom additions and attached garages

Who Can Apply and How
CSL and HIC holders must register their licenses with the Building Department in person with the original cards. A homeowner who owns and lives (or will live) on the parcel can do the work, using the homeowner warning and license exemption forms.
Apply through ViewPoint Cloud (OpenGov). Questions go to the Building Department at 781-431-1019.
Energy Code Compliance: The Part That Holds Up Most Permits
Wellesley's Specialized (Opt-In) Energy Code took effect January 1, 2024.
At permit: New homes and large additions need a projected HERS rating report. The town's checklist still mentions ResCheck from the older code, so confirm the current path with the Building Department; we model both.
At final: At final we run the blower door and duct leakage tests and issue the confirmed HERS certificate.
| Project | Energy document |
|---|---|
| New home | Projected HERS report (HERS 42 mixed-fuel / 45 all-electric) |
| ADU | Projected HERS report (HERS 52 / 55) |
| Addition over 1,000 sq ft or over 100% of the home | Projected HERS report (HERS 65 / 70) |
| Smaller addition or alteration | REScheck or the prescriptive path, if the inspector accepts it |
| Commercial up to 20,000 sq ft | COMcheck plus a whole-building blower door test |
Home Energy Efficiency Consultants prepares the projected HERS report from your plans, usually in about one business day after the quote is accepted, then does the pre-drywall inspection, blower door and duct leakage tests and the confirmed HERS certificate. See our stretch code report for Wellesley permits page for what's in the report, EV-ready and solar-ready rules, and when Phius applies.


Other Approvals You May Need in Wellesley
- Fire Department, Board of Health (septic, teardowns, demolition) and DPW (water, sewer, street openings, drainage)
- Historic District Commission in a designated district; Historical Commission demolition review for homes built on or before 1949
- Natural Resources Commission near wetlands or streams
- Select Board and DPW for new curb cuts; ZBA special permit for some nonconforming-structure additions
- Large House Review by the Planning Board when TLAG exceeds the district threshold (typically 3 to 4 months)
Permit Fees and Timing
Fees: $15 per $1,000, minimum $100, for new homes and additions (valued at $200 per sq ft of finished space). Residential CO $50 (schedule effective April 1, 2025). Always check the current schedule before you apply.
Review time: Generally 7 to 14 business days for permit review; Large House Review adds about 3 to 4 months.
Final Inspection and Certificate of Occupancy
For new homes and large additions, the confirmed HERS rating (with passing blower door and duct leakage results) is part of the close-out paperwork. Book the final test before the building inspector's final so the paperwork is ready.
Local rules to know:
- Large House Review (Zoning Bylaw Sec. 5.9)
- The Inspector notifies abutters within 300 ft before issuing a permit for new structures of 300 sq ft or more
Building Permit FAQ for Wellesley
What do you need for a building permit in Wellesley, MA?
For a new home or addition: the online application, scaled construction plans, a certified plot plan by a land surveyor, contractor CSL/HIC, insurance and workers' comp paperwork (or a homeowner exemption), any zoning or historic approvals, and energy code compliance documentation. New homes and large additions need a projected HERS rating report.
Do I need a HERS rating for a building permit in Wellesley?
For a new home, yes, and also for additions over 1,000 sq ft or more than 100% of the existing home. The rater models your plans for the permit (projected HERS report), then tests the finished house (blower door and duct leakage) for the confirmed HERS rating. Smaller additions and alterations can usually use REScheck or the prescriptive path.
What energy code does Wellesley follow?
Wellesley's Specialized (Opt-In) Energy Code took effect January 1, 2024.
Where do I apply for a building permit in Wellesley?
At the Building Department, 888 Worcester Street, Suite 160, Wellesley, MA 02482 (781-431-1019), through ViewPoint Cloud (OpenGov).
Who can pull a building permit in Wellesley?
CSL and HIC holders must register their licenses with the Building Department in person with the original cards. A homeowner who owns and lives (or will live) on the parcel can do the work, using the homeowner warning and license exemption forms.
How much does a building permit cost in Wellesley?
$15 per $1,000, minimum $100, for new homes and additions (valued at $200 per sq ft of finished space). Residential CO $50 (schedule effective April 1, 2025). Check the current fee schedule before you apply.
How long does a building permit take in Wellesley?
Generally 7 to 14 business days for permit review; Large House Review adds about 3 to 4 months.
Sources and Related Pages
Checked on Wellesley's official pages in October 2026. Rules and fees change, so confirm with the building department before you file.
- Wellesley Building Department
- Wellesley residential permit checklist
- Wellesley fee schedule
- Mass.gov: energy code adoption by municipality
Related: Stretch code report for permitting · HERS rating in Wellesley · Blower door testing · What triggers a HERS rating. We cover Wellesley from our Framingham office at 68 South St.
Need the Energy Report for Your Wellesley Permit?
Send your plans today. Most projected HERS reports are ready in about one business day after the quote is accepted.
Mass Save®-Listed HERS Rater
Trusted Partner — Verified
Partner
Passive House Verifier
Member★★★★★136 Google
Reviews
The Phius Certified Verifier logo is used under license from Phius.