To get a building permit in Burlington, apply to the Building Department through OpenGov permitting portal. For a new home or addition you will usually need the application, scaled plans, a surveyor's plot plan, contractor license and insurance paperwork (or a homeowner exemption), a workers' comp affidavit and energy code documentation. Burlington follows the base Massachusetts energy code (2021 IECC with state amendments), so new homes show energy compliance either prescriptively (REScheck) or with a HERS rating from a RESNET-certified rater.
Burlington building department
Building Department
25 Center Street, Burlington, MA 01803
781-270-1615
Apply: OpenGov permitting portal
Burlington Building Permit Checklist
What Burlington asks for on a new home, addition or major renovation, from the Burlington permit pages. Bring all of it the first time and the review moves faster.
- Online building permit application
- Construction plans
- Plot or site plan when required
- Contractor license and insurance information
- Stamped engineering for LVL or I-joist floor systems
- Construction control documents and debris affidavit depending on scope
- Floodplain Development Permit or ADU acknowledgement form if applicable

Who Can Apply and How
Applications need contractor license and insurance information; changing general contractors requires a new application and fees.
Apply through OpenGov permitting portal. Questions go to the Building Department at 781-270-1615.
Energy Code Compliance in Burlington
Burlington is not on the state's Specialized Code list or the Stretch Code adopter list; the town's codes reference lists the 2021 IECC (the Massachusetts base energy code).
At permit: Under the base code, new homes can show compliance prescriptively (REScheck) or with a HERS rating (the Energy Rating Index path). Many builders still use a HERS rating because it gives more design flexibility and is needed for Mass Save and ENERGY STAR programs.
At final: New homes still need a blower door test (3.0 ACH50 under the Massachusetts code) and duct testing where ducts are outside conditioned space.
| Project | Energy document |
|---|---|
| New home | REScheck/prescriptive, or a HERS rating (Energy Rating Index path) |
| ADU | REScheck/prescriptive, or a HERS rating |
| Addition over 1,000 sq ft or over 100% of the home | REScheck/prescriptive, or a HERS rating |
| Smaller addition or alteration | REScheck or the prescriptive path, if the inspector accepts it |
| Commercial up to 20,000 sq ft | COMcheck plus a whole-building blower door test |
Home Energy Efficiency Consultants prepares the projected HERS report from your plans, usually in about one business day after the quote is accepted, then does the pre-drywall inspection, blower door and duct leakage tests and the confirmed HERS certificate. See our stretch code report for permitting page for what's in the report, EV-ready and solar-ready rules, and when Phius applies.


Other Approvals You May Need in Burlington
- Conservation Department near wetlands or conservation areas
- Planning Board site plan and/or special permit for projects other than single-family homes
- Historical Commission demolition delay review for homes older than 100 years
Permit Fees and Timing
Fees: Residential building permit: $13 per $1,000, minimum $50 (schedule as of August 2026). New residential construction is valued at $150 per sq ft of finished space. Always check the current schedule before you apply.
Review time: Allow at least two weeks for most projects.
Final Inspection and Certificate of Occupancy
For new homes and large additions, the confirmed HERS rating (with passing blower door and duct leakage results) is part of the close-out paperwork. Book the final test before the building inspector's final so the paperwork is ready.
Local rules to know:
- Construction hours: 7am-7pm weekdays, 9am-7pm Saturday, no Sundays or holidays
- No temporary certificates of occupancy
Building Permit FAQ for Burlington
What do you need for a building permit in Burlington, MA?
For a new home or addition: the online application, scaled construction plans, a certified plot plan by a land surveyor, contractor CSL/HIC, insurance and workers' comp paperwork (or a homeowner exemption), any zoning or historic approvals, and energy code compliance documentation. New homes and large additions need a projected HERS rating report.
Do I need a HERS rating for a building permit in Burlington?
Not always. Burlington follows the base energy code, so a new home can comply prescriptively (REScheck) or with a HERS rating. A HERS rating gives more design flexibility and is required for Mass Save new construction incentives and ENERGY STAR. New homes still need a blower door test.
What energy code does Burlington follow?
Burlington is not on the state's Specialized Code list or the Stretch Code adopter list; the town's codes reference lists the 2021 IECC (the Massachusetts base energy code).
Where do I apply for a building permit in Burlington?
At the Building Department, 25 Center Street, Burlington, MA 01803 (781-270-1615), through OpenGov permitting portal.
Who can pull a building permit in Burlington?
Applications need contractor license and insurance information; changing general contractors requires a new application and fees.
How much does a building permit cost in Burlington?
Residential building permit: $13 per $1,000, minimum $50 (schedule as of August 2026). New residential construction is valued at $150 per sq ft of finished space. Check the current fee schedule before you apply.
How long does a building permit take in Burlington?
Allow at least two weeks for most projects.
Sources and Related Pages
Checked on Burlington's official pages in October 2026. Rules and fees change, so confirm with the building department before you file.
- Burlington permits and applications
- Burlington building permit fees (August 2026)
- Burlington construction documents
- Mass.gov: energy code adoption by municipality
Related: Stretch code report for permitting · HERS rating in Burlington · Blower door testing · What triggers a HERS rating. We cover Burlington from our Everett office at 371 Main St.
Need the Energy Report for Your Burlington Permit?
Send your plans today. Most projected HERS reports are ready in about one business day after the quote is accepted.
Mass Save®-Listed HERS Rater
Trusted Partner — Verified
Partner
Passive House Verifier
Member★★★★★136 Google
Reviews
The Phius Certified Verifier logo is used under license from Phius.